The Development of First Plasma Operations on ITER

ORAL

Abstract

ITER construction is well underway and first plasma operations are planned at the end of 2025. Plant system commissioning has begun and will proceed up to the closure of the cryostat in late 2024, which defines the start of integrated commissioning, including that of the Central Interlock System (CIS), the Plasma Control System (PCS), and associated diagnostics to ensure investment protection and central control functions can be carried out. An independent system will also be commissioned for superconducting magnet protection to avoid approaching force, field, and temperature limits. First plasma scenarios in hydrogen with BT = 2.65 T will first attempt Ohmic breakdown within a neutral pressure range of 0.3 mPa < p < 0.7 mPa, limited by runaways at the low end and by inability to ensure Ip ≥ 100 kA for ≥ 100 ms at the high end. If Ohmic breakdown is unsuccessful, electron cyclotron heating will be added in 0.83 MW steps for short pulses (< 300 ms), possibly up to 6.7 MW injected at 2nd harmonic. The PCS must ensure that Ip < 1 MA to stay within structural limits of the vacuum vessel supports to the temporary poloidal stainless steel limiters. A backup option to improve breakdown is to operate at full toroidal field of 5.3 T with 1st harmonic ECH after magnet commissioning.

Presenters

  • Joseph A Snipes

    ITER Organization

Authors

  • Joseph A Snipes

    ITER Organization

  • Himank Anand

    ITER Organization

  • Ken Blackler

    ITER Organization

  • Peter C de Vries

    ITER Organization

  • Juan Luis Fernandez-Hernando

    ITER Organization

  • Yuri Gribov

    ITER Organization

  • Mark Andrew Henderson

    ITER Organization

  • Jean-Yves Journeaux

    ITER Organization

  • Tim Luce

    ITER, ITER Organization

  • Ignacio Prieto-diaz

    ITER Organization

  • Anders Wallander

    ITER Organization

  • Luca Zabeo

    ITER Organization

  • Isabel Nunes

    IST Lisbon Portugal